Construction Info

Recent photos of construction progress along the trail are
available here

Rail Trail Construction FAQ is available here

For Chelmsford status and questions contact Cynthia McLain

For Westford status contact Emily Teller

Phase 1 Memorandum of Agreement details here.

Amenities and Acquistions

The Friends of the BFRT are assisting with amenities, such as benches and bike racks, and the acquisition of the Phase 3 portion of the railroad right of way (ROW). The rail trail will also need regular maintenance for which the Friends will provide support. More information here

Sponsor a mural on the Bruce Freeman Rail Trail

RAILs, TRAILs and TIES

This column in the Chelmsford Independent has information about the current progress on the trail.

June 17, 2009 - Adding artistic touches to the Rail Trail

March 25, 2009 - With arrival of spring, work on bicycle trail gets rolling

November 13, 2008 - Take care near the worksites

October 30, 2008 - Connecting with the Freeman Rail Trail

September 18, 2008 - Work on Freeman Rail Trail rolls along

September 4, 2008 - Keeping track of the bicycle trail

July 3, 2008 - Rail trail construction shifts to the Center

June 5, 2008 - New bicycle and pedestrian committee

April 24, 2008 - Where will the rail trail run?

March 6, 2008 - A real count of potential trail users
Topic: Statewide trail usage counts on Sept. 8, 2007

January 17, 2008 - Clearing of the rail trail completed
Topic: Phase 1 construction

December 26, 2007 - Greenway slated for rail trail
Topic: Concord River Greenway and Greenway Connector Trail

December 12, 2007 - Many components to rail trail
Topic: Bruce Freeman Rail Trail Coordinating Committee

November 20, 2007 - Work on the bike trail has started
Topic: Phase 1 construction

September 26, 2007 - Bike trail groundbreaking set
Topic: Brief history of Phase 1

September 20, 2007 - New Column
Topic: Phase 1 construction

Related Links

History of the Railway in Chelmsford Details Here

Chelmsford Land Conservation Trust http://www.clct.org/

Chelmsford Historical Society http://www.chelmhist.org/

Lowell Parks and Conservation Trust http://lowelllandtrust.org/

Middlesex Canal Association http://www.middlesexcanal.org/

 

PHASE 1 Construction Information

Overview

The trail is currently closed to use. Safety hazards exist in many areas.

Construction is slated to be complete in summer 2009. The section of trail under construction extends from the Lowell/Chelmsford line near Cross Point, through Chelmsford Center, to the intersection of Route 27 and Route 225 in Westford. When completed, the trail will be 10-foot wide pavement with a 2-foot wide packed shoulder on each side. The surface of the shoulders will be level with the surface of the trail.

Please stay off the rail trail corridor during construction, to avoid injury from equipment, debris, and other hazards created by the construction process. Heavy equipment is used during construction and the entire rail corridor is considered a work zone.

Installation of vinyl-coated chain link fencing and landscaping is ongoing. Curbing is being installed at 56-61 Central Square, next to Old Town Hall. Adjustments were made to the plans to minimize impacts on parking.

As work progresses on the trail, it seems inviting to use but the road intersections still make use of the trail unsafe. Intersections with roads are not marked at this point and present a hazard. Temporary fencing has been installed to restrict access since the trail is still under construction.

Curbing for the rail trail has been installed between the parking lots in the rear of Village Square and 30 Chelmsford St. (Chelmsford Cyclery) to 60 Chelmsford St. (Highlights Salon). Curbing has also been installed in the area behind Ginger Ale Plaza (Bertucci's).

Installation and grading of the gravel base and installation of the binder course for most of the trail was completed by the end of 2008. The gravel base and binder course for the remaining areas is being installed during June and July. Paving, followed by installation of shoulders and work on the intersections could begin by mid-July.

The total pavement thickness will be 3 inches. Until the shoulder material is installed, there will be a drop off along the edge of the trail surface. This kind of drop off can be dangerous and is known to have resulted in ambulance rides. For your safety, please stay off the trail during construction.

Answers to Frequently Asked Questions (FAQs) about Rail Trail Construction are available here.

June 12, 2009 Current Project Status

Chain Link Fence installation  on –going from Chelmsford to Westford.
Planting and landscaping work on-going.
Construction of path thru Chelmsford center (Domino’s) began week of 6/22/09.
Curb to be installed in early July with gravel sub-base to follow.

Additional Information

Top course paving is tentatively scheduled for mid-July.
Gravel shoulders to be installed following paving.
Intersection enhancements/safety features to follow.
Substantial completion is anticipated for mid-August 2009.

Construction Update Archive

Construction Benchmarks

Apr 2007 Phase 1 advertised for construction bids

Jun 2007 Construction bids opened

Aug 2007 Notice to Proceed issued

Aug 2007 Preconstruction meeting

Oct 2007 Groundbreaking ceremony

Dec 2007 Erosion control installation completed

Jan 2008 Clearing of trees and undergrowth from rail bed completed

Mar 2008 Track removal completed

May 2008 Tie removal completed

Jun 2008 Drainage system installation complete

Jul 2008 Granite curbing installation at Village Sq. and 30-60
Chelmsford St. completed

Nov 2008 Gravel base installation and grading completed

Nov 2008 Binder course installation completed

Nov 2008 Gravel base installation and grading completed for most of trail

Nov 2008 Binder course installation completed for most of trail

Dec 2008 Slope construction completed for most of trail

Dec 2008 Granite curbing installed behind Ginger Ale Plaza (Bertucci's)

Dec 2008 Bridges completed except for railings and travel surface

Please see the MassHighway project web site for status and contact information.

The number for the answering machine in the Resident Engineer's field office is 978-256-3947. Please leave the following information: name, daytime phone number, address (for abutters), email address (optional), and a one or two sentence description of the reason for the call.

An email address will lead to a quicker initial response. We will research the question and get back to you. We ask that you review the information on the website before calling.

While waiting for a response, please keep in mind that the Resident Engineer is working on multiple projects.